Cranes GDMJ 40t a GJMJ 4,9t, projekt ALTAY II a III, Kazakhstan

 
Year of realization 2014-2015
Customer Metso Minerals (France) S.A.
Project Altay II, Altay III
Place of installation Terekti Ken Bayitu LLP (ТОО Теректы Кен Байту), Kazakhstan, Karaganda Region, Karkaralinsk District, Terekty
Range of delivery
Projekt Altay II
Delivery of bridge cranes, including power supply:
Double girder bridge crane GDMJ 40t/16,73m
Single girder bridge crane GJMJ 4,9t/15,295m 
 
Project Altay III
Delivery of bridge cranes, including power supply:
Double girder bridge crane GDMJ 40t/21,43m
Single girder bridge crane GJMJ 4,9t/17,4m
 
Supervision in Kazakhstan, performed by our Russian partner, Company "PTO Machine-Systems". Commonly for the projects Altay I and Altay II. 
 
Year of realization 2014-2015
Customer Metso Minerals (France) S.A.
Project Altay II, Altay III
Place of installation Terekti Ken Bayitu LLP (ТОО Теректы Кен Байту), Kazakhstan, Karaganda Region, Karkaralinsk District, Terekty
Range of delivery
Projekt Altay II
Delivery of bridge cranes, including power supply:
Double girder bridge crane GDMJ 40t/16,73m
Single girder bridge crane GJMJ 4,9t/15,295m 
 
Project Altay III
Delivery of bridge cranes, including power supply:
Double girder bridge crane GDMJ 40t/21,43m
Single girder bridge crane GJMJ 4,9t/17,4m
 
Supervision in Kazakhstan, performed by our Russian partner, Company "PTO Machine-Systems". Commonly for the projects Altay I and Altay II. 

Production of cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,285m

Production of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285m

Production of cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,285m

Production of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t, 16,73m and GJMJ 4,9t, 15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mProduction of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285m

Dispatch of cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,285m

Dispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285m

Dispatch of cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,285m

Dispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t, 16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285mDispatch of cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,285m

Cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,295m after mounting v Terekty, Kazakhstan

Cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, KazakhstanCranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, KazakhstanCranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, Kazakhstan

Cranes GDMJ 40t/16,73m and GJMJ 4,9t/15,295m after mounting v Terekty, Kazakhstan

Cranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, KazakhstanCranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, KazakhstanCranes GDMJ 40t-16,73m and GJMJ 4,9t-15,295m after mounting v Terekty, Kazakhstan